(Querist) 05 July 2012 This query is : Resolved 
Sir/Madam,
I am from Mayiladuthurai, Tamilnadu. I have a High tension line from TNEB for my organization. As per The Electricity Act & other statutory laws in Tamilnadu, is it mandatory to obtain temporary electricity connection for construction of new building or can I extend my high tension line for this purpose?
ajay sethi (Expert) 05 July 2012
better obtain permission to be on safe side .
Yukendran (Querist) 05 July 2012
Sir, thanks for the reply. Anti Power Theft Squad (APTS) has already visited our place and has fined us for around 1.3lakh rupees, when our temporary connection application was pending with TNEB. I heard that appeal can be made & hence want to know whether HT line can be extended for construction purpose as per the statutory laws?
Kiran Kumar (Expert) 06 July 2012
what will u get in appeal when your action was illegal.

pending application does not provide you any right to violate the law.

follow the legal methods.
Yukendran (Querist) 06 July 2012
Sir, thank you for the reply. My pending application to TNEB was only an additional input. My query is "I want to know whether HT line can be extended for construction purpose as per the statutory laws?" I am not sure whether HT line can be extended for such purpose.
R.RAJENDRAN (Expert) 06 July 2012
H.T LINE CAN NOT BE EXTENDED FOR YOUR CONSTRUCTION OF PURPOSE AS IT WOULD AMOUNT OF MISUSE OF H.T LINE, ATTRACTING MAXIMUM PENALTY , IF DETECTED.
Yukendran (Querist) 06 July 2012
Thank you sir, for the clarification.