consumer
PRAKASHCHANDRA MARU
(Querist) 29 July 2009
This query is : Resolved
hello all experts
i have lodged the complaint in foram against pvt builder company for the non construction of the flat in stipulated time on the place there is only primer work started and stop from the one year
on the time of primary hearing the question was asked by the member that the builder can give possession at any time because the stipulated time is not over the complaint is already registered and now the case is onthe stageof evideance now i would like to get do panchnnama pf the place where the such construction not take place and it is impossible to complete work within the time limit pls mention under which section i have to apply for the demand of the panchnama and also state the authoryty if u have thanks in advance
Y V Vishweshwar Rao
(Expert) 30 July 2009
You can file Photos of the site with Primary construction and the opposite party may not dispute the Photos . You may request the Dist Consmer Forum to inspect the Site or to get it inspected by any one appointed by DCF !
Manish Raghav
(Expert) 30 July 2009
Dear prakash
you can apply under order 26 rule 9 of the CPC foe the appointment of local commissioner,
Jithendra.H.J
(Expert) 30 July 2009
it is rightly suggested by Manish Raghav, in supporting the commisioner report u can also produce the photos
(it has to be along with the -ve and the reciept)
Kiran Kumar
(Expert) 30 July 2009
advice given is good.
if u need some documents from the state authorities then apply for the certified copies with them.
if this is not possible, then u can move an application under Right to Information Act.
Local commissioner option is a good one.
Forum can even appoint an expert to make an assessment of the situation whether the work can be completed within a stipulated time.
PRAKASHCHANDRA MARU
(Querist) 30 July 2009
yes sir i given the applicatrion for the assesment but it was told to me for the inform the section so mr kiran kumar sir if u know the section pls inform