provisions of re tendering
eswarkumarpotti
(Querist) 07 April 2010
This query is : Resolved
dear respected Sirs,
Good afternoon
our orgnaisation has outsourced the conservancy servicces to regisered lienced contractor for the financical of 2010-2011 as he has quoted the lowest bid accordingly the mangement and contractor enter into an agreement, whereas the contractor unable to pay the minimum wages and also not ready to execute the contract . by seeing this situation, noe the orgnaisation has proposed to re tender the conserveacy services to liecensed contractor. for this we are in need of provisions and rule position on the subject and the law governing the retendering procedure. pl educate us on the procedure to be followed while doing so.
thanking you all respected EXperts.
s.subramanian
(Expert) 03 November 2010
The same procedure that you followed earlier has to be repeated in the retender.