Regarding excessive delay in concluding execution petition before consumer forum

In one of the Execution Petition against the JDR-Govt Authority, the District consumer Forum is taking inordinate delay in concluding the case. Execution application was filed more than 12 years back and the JDR has not complied the order of the forum as well as not paid any compensation to DHR, sr. citizen. Its almost a year that the matter was kept reserved for orders but still it is pending. Its unfortunate that the poor DHR being the Sr. Citizen is fighting before the consumer forum for more than 12 years that too with the Execution application and frustrated with the excessive delay before the district consumer forum Therefore, could some one advise on various options / remedies available for DHR to get the case disposed of at the earliest? Thanks !


Learning

 2 Replies

Dr. MPS RAMANI Ph.D.[Tech.] (Scientist/Engineer)     08 June 2017

When I saw "excessive delay in execution", I thought the matter referred to Rajiv killers.

NATARAJAN IYER (Proprietor)     17 June 2017

12 years !!!

something seems wrong somewhere.

You can approach the State Commission although for orders passed at lower court, 

execution has to happen from that lower court only.

You can meet the Registrar at the State Commission and seek his advise.

Also from the national commission web-site, find out when the bench has a sitting at your city.

You can present your matter before the national commission bench at your city and they might pass 

suitable orders.

 