Vinayak Bhnadarkar (na)     29 December 2014

Bocw act

Im working in educational institute governed by the UGC,hence-central government.The institute is building campuses in various states.The institute has appointed PMC-project management consultant,architects and contractor for building the buildings.
1.Will BOCW act be applicable to the institute/PMC/contractor?
2.Will the institute or contractor require to pay BOCW cess?if yes, then at what rate? and time?
3.What other legal obligations will the contractor need to satisfy under the BOCW Act?



 1 Replies

SANJEEV KUMAR YADAV (dm)     30 December 2014

Yes Bocw act 1996 is applicable till the construction is not over. Your institute & the contractor both has to take Bocw registration in form 2. The contractor has to make beneficiary all  the labour involved in construction. Beside this contactor has to take Workmen compensation policy.

the cess has to be paid by the principals employers that is your Institute @ 1% of the cost of construction minus the cost of land.

the contactor has to take Bocw registration. Make all his labourers beneficiary by filling form V.

had to fill form 4 to inform the labour department for start and ending of the project. 

Has to maintain all CLRA records . Women register. Muster roll. Wages sheet signed by the Principal employer, OT, damages & loss, fine, advance registers.

have take safety as priority for its labourers, build rest room, seize rate toilets for male female" 

if labour strength more than 250 than has to have canteen, first aid room, medical check up of all the operators,

if labour more than 500 than ambulance room and doctor visits and all the time male nurse.

 

its better you read the act