Pradip Bajaj   27 March 2016

Sec. 80 c.p.c.

Sir,

A work order executed in the year 2001 for supply of some furniture items to the SDO(Civil) on his order for supply the same for Rs. 4 lcs.

In the year 2005 Rs. 2 lacs paid.

In the year 2010 Rs. 1 lac paid.

In the year 2013, WP(C) case U/s 80 CPC was filed in the High Court, the High Court also directed the depatment to pay the amount assoon as possible. and a copy of the judgment was also submitted with the department.

But till now the balance due of Rs, 1 lac is outstanding.

Q:-

1] What steps are available for the recovery of balance amount?

2] Can interest or any compensation may be charged on the total/ partial/ balance amount ?

3] Any legal remedy available? 



 2 Replies

adv. rajeev ( rajoo ) (practicing advocate)     27 March 2016

You will have to file an execution petition to recover the amount as per the decree

 

1 Like

Augustine Chatterjee,New Delhi (Advocate & Solicitor at Law)     27 March 2016

An execution of the said order shall have to be filed for the recovery of the said amount . Interest shall also be awarded by the court provided the same has been asked for by you in the petition .