1. There is no provision under the MOFA, to grant Conveyance of the plot to the Society.
2. MOFA, only provides provisions / directions that the Builder should execute the Conveyance with 4-6 months and the relevant Punishment that would be applicable.
3. In the instant matter, if the Builder is ready to execute the Society Plot Conveyance Deed, then the Society officer bearers and the Builder can do the same before the Registrar of Sub-Assurances.
4. Typically all the Conveyance Expenses have to be borne by the Builder / Developer.
Keep Smiling .... Hemant Agarwal