Allotment letter

(Querist) 22 June 2013 This query is : Resolved 
I HAD PURCHASED A 2 BHK FLAT IN A UNDERCONSTRUCTION PROJECT. THE RATE WAS VERY
REASONABLE.I PAID FULL AMOUNT THRO CHQ.ALL ENTRIES IN PASS BOOK REFLECTS THE AMT PAID TO THE DEVELOPER. THE DEVELOPER GIVEN ME A
SIMPLE ALLOTMENT LETTER ON WHICH FLAT NO,FLOOR NO. & THE AMT IN WHICH OUR DEAL FINALISED. NOW THIS PROJECT IS BEING DELAYED BY 3 YRS DUE TO MUNICIPAL PASSING AUTHORITIES
THIS BUILDER IS DEVELOPING VARIOUS PROJECT IN THE CITY BY DIFFERENT COMPANY NAMES WITH SAME PROMOTERS/PARTNERS.SOME OTHER PROJECTS ARE NEAR TO COMPLETION.WE ASKED TO TRANSFER
OUR INVESTMENT TO HIS COMPLETE PROJECT & HAND OVER THE POSSESION IN COMPLETE PROJECT.
BUT HE IS NOT AGREEING OUR REQUEST.

WHAT LEGAL ACTION WE CAN TAKE<
Devajyoti Barman (Expert) 22 June 2013
The sale agreement needs to be checked. If there is mo escape route out of delay from civic authorities then you can claim damages from consumer forum.