Upgrad
LCI Learning

Share on Facebook

Share on Twitter

Share on LinkedIn

Share on Email

Share More

Insolvency Of Petitioner No Bar To Arbitration; Serving Officer Of Army Can Not Be Named An Arbitrator: Delhi High Court

Sanskriti Tiwari ,
  15 March 2024       Share Bookmark

Court :
Delhi High Court
Brief :

Citation :
2024 DHC 2787

CASE NAME:

Godavari Projects (JV) vs. Union of India

CASE DATE:

4th March, 2024

PARTIES:-

Petitioner: Godavari Projects (JV)

Respondent: Union of India

BENCH/JUDGE:

Justice Sachin Datta

IMPORTANT PROVISIONS:-

1.Section 11(6) of the Arbitration and Conciliation Act, 1996 (A&C Act):-

This section pertains to the appointment of arbitrators. 

2Sections 28 of the Indian Contract Act, 1872:-

Section 28 deals with agreements in restraint of trade.

3.Section 29 of the Indian Contract Act, 1872:-

Section 29 pertains to agreements void for uncertainty. 

4.Section 12 of the Arbitration and Conciliation Act, 1996 (A&C Act):-

Section 12 outlines the disclosure obligations of an arbitrator.

SUBJECT:-

A construction dispute arose when the respondent cancelled a Mumbai project contract, alleging petitioner's violations. The petitioner, citing Force Majeure and termination options, initiated arbitration. The court, addressing objections, appointed an independent arbitrator. The case involving issues of insolvency, contract termination and the validity of arbitration clauses, now awaiting resolution through arbitration proceedings.

OVERVIEW:-

  • The case revolves around a dispute stemming from the termination of a contract related to the construction of dwelling units in Mumbai. 
  • The petitioner initiated arbitration proceedings seeking resolution of the disputes, which were contested by the respondent. 
  • Central to the case is the interpretation of the arbitration clause outlined in the contract, specifically under Section 11(6) of the Arbitration and Conciliation Act. 
  • The petitioner justifies the termination based on circumstances beyond their control, citing government memorandums, while the respondent raises objections regarding breach of contractual obligations and the validity of the termination. 
  • The court is tasked with adjudicating these disputes and determining the enforceability of the arbitration clause in light of the legal precedents and contractual provisions.

ISSUES RAISED BEFORE THE COURT:-

  1. Whether the arbitration agreement stipulating a serving officer of the respondent as arbitrator is valid?
  2. Whether the government memorandums on Force Majeure and contract termination apply to the petitioner's case?
  3. Whether insolvency proceedings against a petitioner constituent affect the petitioner's right to initiate arbitration?
  4. Whether the petitioner's termination of the contract and initiation of arbitration proceedings are valid?
  5. Whether the court has jurisdiction to entertain the petition under Section 11(6) of the Arbitration and Conciliation Act, given the ongoing insolvency proceedings?

CONTENTIONS RAISED ON BEHALF OF THE PETITIONER:-

  • The learned counsel for the petitioner contended that the termination of the contract was justified, citing circumstances beyond their control. They argued that the initiation of arbitration proceedings was in adherence to the arbitration clause outlined in the contract.
  • The petitioner further asserted that the government memorandums issued during the COVID-19 pandemic provided a valid basis for invoking the Force Majeure Clause. They contended that this absolved both parties from financial repercussions arising from the termination of the contract.
  •  It was argued by the petitioner that their alleged insolvency did not affect their capacity to seek arbitration. They argued that insolvency proceedings only restricted actions against the corporate debtor, not actions by the debtor itself and thus their initiation of arbitration was lawful.
  • The petitioner vehemently contested the respondent’s accusations of breach of contractual obligations. They maintained that the termination of the contract by the respondent was pre-emptive and aimed at countering the petitioner’s legitimate claims, which were compliant with the contract terms and legal requirements.
  • The petitioner advocated for a liberal interpretation of the arbitration clause in the General Conditions of Contract. They argued that objections raised by the respondent on procedural grounds should not detract from the fundamental purpose of arbitration, which is to ensure equitable resolution of disputes.
  • The petitioner asserted that the court retained jurisdiction to entertain the petition under Section 11(6) of the Arbitration and Conciliation Act. They argued that insolvency proceedings did not preclude their right to seek arbitration and thus their recourse through arbitration remained valid and enforceable.

CONTENTIONS RAISED ON BEHALF OF THE RESPONDENT:-

  • The learned counsel for the respondent argued that the termination of the contract by the petitioner was unjustified and in violation of their contractual obligations. They contended that the petitioner’s initiation of arbitration proceedings was premature and not in accordance with the arbitration clause outlined in the contract.
  • It was further contended by the respondent that the government memorandums issued during the COVID-19 pandemic did not provide a valid basis for invoking the Force Majeure Clause. They argued that the petitioner’s reliance on these memorandums was flawed and did not absolve them from their contractual obligations.
  • The respondent raised objections regarding the petitioner’s alleged insolvency, questioning their capacity to seek arbitration. They argued that insolvency proceedings against one of the petitioner’s constituents impacted their ability to enter into legal proceedings, including arbitration.
  • The respondent disputed the petitioner’s accusations of breach of contractual obligations and maintained that the termination of the contract by the respondent was lawful and justified. They argued that the petitioner’s failure to fulfil their contractual obligations warranted the cancellation of the contract.
  • The respondent contested the petitioner’s interpretation of the arbitration clause in the General Conditions of Contract, arguing that the clause clearly outlined the procedure for arbitration and did not permit premature initiation of arbitration proceedings.
  • Additionally, the respondent argued that the court lacked jurisdiction to entertain the petition under Section 11(6) of the Arbitration and Conciliation Act due to the ongoing insolvency proceedings against one of the petitioner’s constituents. They contended that arbitration proceedings should be stayed until the resolution of the insolvency proceedings.

ANALYSIS BY THE COURT:-

  • Regarding the petitioner’s reliance on government memorandums issued during the COVID-19 pandemic, the court observed that the applicability of Force Majeure Clause needed thorough examination to determine its impact on the contractual obligations of both parties.
  • The court acknowledged the respondent’s objections regarding the petitioner’s alleged insolvency and recognized the need to address jurisdictional issues arising from the ongoing insolvency proceedings.
  • The court observed that further examination was required to ascertain whether the termination was justified under the contractual terms.
  • Regarding the interpretation of the arbitration clause, the court observed that a liberal approach should be adopted to ensure equitable resolution of disputes, while also upholding the procedural requirements outlined in the contract.
  • The court noted the need to balance the rights and obligations of both parties while determining the jurisdiction of the court to entertain the petition under Section 11(6) of the Arbitration and Conciliation Act, particularly in light of the ongoing insolvency proceedings affecting one of the petitioner’s constituents.

JUDGMENT:-

The court, after considering the arguments and legal precedents presented by both parties, issued its judgment. It deemed the petitioner’s termination of the contract and initiation of arbitration proceedings valid, supported by government memorandums during the COVID-19 pandemic. The petitioner’s alleged insolvency did not impede their capacity to seek arbitration and the respondent’s objections regarding breach of contractual obligations are dismissed. The court interpreted the arbitration clause liberally, retaining jurisdiction to entertain the petition despite ongoing insolvency proceedings. Mr. Justice (Retd.) Krishna Murari was appointed as the Sole Arbitrator, with the parties sharing the arbitrator’s fee and costs equally. All rights and contentions are kept open for the arbitrator’s determination. This judgment is final and binding, disposing of the present petition accordingly.

CONCLUSION:-

The case underscores the complexities inherent in contractual disputes, particularly in the context of unforeseen events. It highlights the importance of clear contractual provisions and the need for parties to adapt to changing circumstances while upholding their contractual obligations. The court’s decision to appoint a Sole Arbitrator reflects a commitment to resolving disputes through alternative means, fostering a fair and efficient resolution process. Ultimately, the case serves as a reminder of the importance of effective contract management and the significance of arbitration in achieving equitable outcomes amidst legal challenges and uncertainties
 

 
"Loved reading this piece by Sanskriti Tiwari?
Join LAWyersClubIndia's network for daily News Updates, Judgment Summaries, Articles, Forum Threads, Online Law Courses, and MUCH MORE!!"



Published in Others
Views : 564




Comments





Latest Judgments


More »