YOGENDRA SINGH   01 March 2020

Delay in possession of flat

Booked flat in Dec 2011 in Lucknow. Possession date was 31 Dec 2013. As per agreement I paid full amount before 31Dec 2013. In case of delay builder has to pay interest @15% pa. Due to delay and not building as per law, municipality withdrawal all permissions. Builder not getting Completion Certificate. Shall I approach Consumer court before registry of flat or after registry in my name. Can I sell flat after registry and still claim interest and compensation from builder?


Learning

 1 Replies

Adv Deepak Joshi +917017821512 (Advocate)     01 March 2020

Dear Querist,

Serve legal notice for delay in possession and then approach consumer forum under deficiency in serve against the builder.

 

Regards
Deepak