Upgrad
LCI Learning

Share on Facebook

Share on Twitter

Share on LinkedIn

Share on Email

Share More

Developer given less area, not in confirmity with agreement

(Querist) 07 April 2017 This query is : Resolved 
Respected Advocate kakde Sir, Thanks for your advise on my other query Of Dish direct matter.In my present accommodation in Thane , builder has given less area (not as per agreed terms mentioned in the agreement.
Possession was taken in April 2011. Is there any time limit to claim the compensation. What is the procedure I have to follow .
I want to file suit in Consumer Court . can you suggest me the process.
A. A Ghaisas.
Kundan Kr. Singh (Expert) 08 April 2017
with in two years you may file consumer complaint
Rajendra K Goyal (Expert) 08 April 2017
Time to file consumer complaint is 2 years.
Hemant Agarwal (Expert) 21 April 2017
IRRESPECTIVE OF "Possession was taken in April 2011"
1. Get a Registered Architects Certificate on the Flat's Layout Plan of the "Current date", which should specify the actual available area of the Flat with drawings.

2. Based on the above Certificate, Issue Legal Notice to Developer, to compensate the loss of space.

3. Based on the above Certificate, and any negative response from the builder, you file your Consumer Grievance petition, even today.

Keep Smiling .... Hemant Agarwal
VISIT: http://www.maharashtra-society-help-forum.com


You need to be the querist or approved LAWyersclub expert to take part in this query .


Click here to login now



Similar Resolved Queries :