(Querist) 28 April 2015
This query is : Resolved
This is re post for the sake of clarity and better response from the experts fraternity.
1)Tenants and landlords filed consent terms in Bombay High Court on 30th June 2013.
2)Land lords have consented to redevelop the building in max.30 months by 30th August 2016.
3) Land lords have entered in to separate agreements and registered them in June 2014 with proposed plan yet to be approved by MCGM and have not provided the approved plan till date.
4) It takes min. 18-24 months to complete the construction work and so landlords are already at fault as they have not commenced the construction.
Pl. advice what tenants should do ?
Should they wait till 30th June 2016 to initiate legal action ?
Devajyoti Barman
(Expert) 29 April 2015
without seeing the consent terms further advice can not be given.
Guest
(Expert) 29 April 2015
If you have posted this query for the sake of clarity and better response from the experts fraternity, you could have asked for more responses in the same original thread, not as a fresh thread.
You could better have made a mention of doubt, if you have any or the reason of your non-satisfaction in the same thread.
Now, what, if you get contradoctory views in reply to your present thread, as compared to the previous answers? Would that prove to clear your doubt, if any?